Construction in Maine will resume next week on an electricity transmission project bringing Canadian hydropower to the New England power grid despite a half-billion dollar cost increase, the head of Avangrid said Thursday.

CEO Pedro Azagra Blazquez said on an earnings call that the cost of the project, originally estimated at around $1 billion, has grown to $1.5 billion as litigation delayed construction and inflation cause prices to creep upward.

MAINE PLANS TO SOURCE HALF ITS ENERGY FROM OFFSHORE WIND BY 2040

Avangrid, the corporate parent of Central Maine Power, partnered with Hydro-Quebec on the power line project — dubbed the New England Clean Energy Connect — to bring 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That represents enough electricity for about 1 million homes.

It received all regulatory approvals but has been plagued by delays and litigation. The developers and Massachusetts utilities are trying to sort out how the cost increases will be shared.

$1B CANADIAN HYDROPOWER TRANSMISSION PROJECT TO BE RENEGOTIATED DUE TO COST INCREASES

The Maine Department of Environmental Protection restored permits for the project in May after a lengthy court battle, but work did not resume immediately because of concerns about the growing costs. The Massachusetts Legislature is advancing legislation allowing transmission service agreements to be renegotiated to recover the cost increases.

The 145-mile power transmission line will stretch from Lewiston, Maine, to the Canadian border, mostly following existing utility corridors. The permit fight was over a new, 53-mile section in western Maine.

Work will resume Aug. 3 at a substation in Lewiston, Azagra said during an earnings call on Thursday. He didn’t elaborate on the timetable for construction on other parts of the project. “Once complete, NECEC will benefit all of New England by reducing the region’s dependence on fossil fuels and providing more stable energy prices,” he said.

The post Maine hydropower project to resume despite $500M price hike appeared first on lawyer.bet.

For more on our Florida practice, see our overview of Florida probate administration. Morgan Legal Group's affiliated New York office also handles New York elder law.

DISCLAIMER: The information provided in this blog is for informational purposes only and should not be considered legal advice. The content of this blog may not reflect the most current legal developments. No attorney-client relationship is formed by reading this blog or contacting Morgan Legal Group PLLP.

Got a Problem? Consult With Us

For Assistance, Please Give us a call or schedule a virtual appointment.